Agra road cave-in after rain: SP leader Nitin Kohli climbs into crater to measure vikas. Watch video – Agra News

A highway cave-in after heavy rain in Uttar Pradesh’s Agra sparked an uncommon protest on Friday, with Samajwadi Social gathering chief Nitin Kohli climbing into the crater utilizing a picket ladder to “measure” the federal government’s vikas (improvement). The dramatic spectacle got here as questions over the standard of highway infrastructure proceed to mount within the state, weeks after the newly inaugurated Kanpur-Lucknow Expressway developed cracks and sinking stretches.

The cave-in occurred in Karmyogi Colony in Agra’s Kamla Nagar space, the place a big part of the highway all of the sudden collapsed, abandoning an enormous crater.

A video, now broadly shared on social media, reveals Kohli climbing down into the pit whereas two males regular the ladder. Standing contained in the crater, he mocks the federal government’s improvement claims, saying, “Is that this how improvement seems to be? Wherever roads have been constructed, there are potholes in every single place.” He additionally dubbed Agra “Gaddha Nagari” (metropolis of potholes), as a substitute of its standard moniker, the Taj metropolis.

Residents described the gaping gap as a “path to the underworld” and blamed poor building high quality for the collapse, saying the rains had uncovered obvious flaws within the metropolis’s infrastructure. In addition they criticised civic authorities for insufficient monsoon preparedness and demanded instant repairs.

Luckily, no car was passing by means of when the highway gave means, narrowly averting a significant accident. The incident triggered panic within the neighbourhood earlier than officers, together with the Basic Supervisor of the Jal Kal Division, reached the spot to examine the injury. Authorities later cordoned off the affected stretch and started evaluation and restore work.

INFRASTRUCTURE UNDER SCANNER

The Agra cave-in comes at a time when the standard of highway infrastructure in Uttar Pradesh is already beneath intense scrutiny following injury to the newly inaugurated Kanpur-Lucknow Expressway.

Barely three weeks after its inauguration, components of the Rs 4,200-crore expressway developed cracks, sinking and floor slippage, forcing authorities to dig up and reconstruct a number of stretches. The Nationwide Highways Authority of India (NHAI) eliminated three engineers related to the mission, initiated action against construction firm PNC Infratech and suspended toll assortment throughout your entire expressway till repairs are accomplished.

SAME STRETCH REPAIRED AGAIN

In accordance with NHAI officers, the preliminary injury in Unnao was confined to a 120-metre stretch, the place round 100 metres of the bituminous floor was repaired, and one other 20 metres was fully reconstructed.

Nonetheless, the issue resurfaced. Suspecting water ingress into adjoining pavement layers, authorities determined to excavate and rebuild a for much longer 300-metre stretch as a precaution. Minor slippages have been later reported at a number of different areas, whereas continued rainfall led to erosion, settlement and crumbling floor materials in a number of patches.

TRAFFIC HIT, SAFETY CONCERNS RISE

Restore work has disrupted site visitors on the expressway, with automobiles travelling in each instructions being routed alongside a single carriageway at a number of areas. Close to the Unnao entry level, motorists have additionally been requested to take U-turns and briefly drive towards the traditional route earlier than becoming a member of the operational carriageway.

Harm has even been reported on the carriageway presently dealing with two-way site visitors, prompting contemporary repairs alongside transferring automobiles. The scenario has raised security considerations on the expressway, which was designed for speeds of as much as 120 kmph.

Whereas NHAI has stated the official velocity restrict stays unchanged, barricades, diversions and ongoing restore work have compelled motorists to decelerate, additional fuelling questions over the standard and sturdiness of not too long ago constructed infrastructure within the state.

– Ends

Inputs from Nitin Upadhyaya

Revealed By:

Priyanka Kumari

Revealed On:

Aug 7, 2026 17:21 IST

Source link

Leave a Reply

Your email address will not be published. Required fields are marked *